Sequence of Operation in Pre Stressed Pre Cast

Layout, Excavation, Dressing & Casting of Pedestals for FOUNDATIONS, providing Foundation Bolts.

Placing of Pre Cast Columns with Corbels in the Foundation Bolts/Pockets and proper alignment.

Fixing of Pre Cast Beams on the Column as per Design.

Fixing the Parapets and gutters.

Placing of Floor Slabs on the Beams as per design.

Providing Topping Concrete on the Slab, Leveling & Waterproofing (wherever desired)

Second Storey and further, as required.

Placement of Walls in position/AAC Block/Brick Masonary to complete and enclose the building, as desired.

The building is then Plastered/Insulation and Metal Sheet Cladding, as required.